§ 68-3708. High impact projects.  


Latest version.
  • A.  An establishment which meets the qualifications specified in the Oklahoma Quality Jobs Program Act, Sections 3602 through 3609 of Title 68 of the Oklahoma Statutes, except that the establishment has an annual gross payroll for new direct jobs, as defined in the Oklahoma Quality Jobs Program Act, projected by the Department of Commerce to equal at least One Million Dollars ($1,000,000.00) but less than Two Million Five Hundred Thousand Dollars ($2,500,000.00) within three (3) years of the anticipated date of receipt of first incentive payment may qualify for payments for the High Impact Projects Payments Fund created in Section 9 of this act pursuant to approval by the Oklahoma Department of Commerce if the establishment provides a number of new direct jobs that is equal to or greater than one percent (1%) of the total labor force of the county in which the establishment locates.  Such establishments shall be deemed "high impact projects".

    B.  1.  High impact projects, upon approval of the Oklahoma Department of Commerce, may receive quarterly incentive payments for a six-year period from the Oklahoma Tax Commission in an amount which shall be equal to two and one-half percent (2.5%) of gross payroll for new direct jobs.

    2.  During the first three (3) years of the six-year period, an approved project may receive quarterly incentive payments irrespective of whether a minimum annual payroll of One Million Dollars ($1,000,000.00) for new direct jobs is achieved.  In the event a minimum annual payroll of One Million Dollars ($1,000,000.00) for new direct jobs is not achieved by an approved project within three (3) years, payments will cease and will not be resumed.

    3.  An approved project which achieves the minimum required payroll during the first three (3) years is eligible to receive incentive payments during the remaining three (3) years of the six-year period.  Provided, in order to receive an incentive payment for any quarter during the remaining three (3) years of eligibility, the approved project must have an actual verified gross payroll which equal or exceeds One Million Dollars ($1,000,000.00) for new direct jobs for the four (4) consecutive calendar quarters immediately preceding the quarter for which application for payment is made.

    C.  Upon approval of such high impact project to receive payments, the Department of Commerce shall notify the Oklahoma Tax Commission in writing and shall provide it with a copy of the application and the approval.  The Tax Commission may require the establishment implementing the high impact project to submit additional information as is necessary for the Tax Commission to verify continuing eligibility for receipt of incentive payments.  Any information submitted in response to such inquiries shall be considered a part of the documentation for qualification and shall be subject to audit by the Tax Commission.

    D.  As soon as practicable after receipt of departmental approval of a high impact project, the Tax Commission shall notify the establishment performing the high impact project of procedures and requirements to receive warrants.  Once the establishment has complied, the Tax Commission shall issue quarterly warrants as long as eligibility continues.

    E.  The prohibition set forth in Section 3607 of Title 68 of the Oklahoma Statutes shall apply to an establishment which receives incentive payments pursuant to the provisions of this section.

Added by Laws 1994, c. 322, § 8, emerg. eff. June 8, 1994.